How primavera shows retention money deduction

Haresh JayanthMember for 20 years 1 month
Created
1
4
0
For any project, in primavera 3.1 how can we show receipt of Advance Payment at the start of the project and also deduction of retention money every month from very running bills in a cash flow.

Kindly explain how primavera will show deductions from RA bills in a cash flow??????

1 reply

Oldest first
  1. 0
    Mk Tse ·
    Consider by resource instead of cost.
    When update, the actual completion amount will include the advance payment.
    The To completion value is less the retention
    However, creat one more activity for collecting the retention

Log in or join to reply