Resourse

Likaa LikaaMember for 20 years 4 months
Created
1
4
0

Hi,

Anyone can tell me how i delet one of assigned resource, means i assigned 3 resourse i want to delet one of them for some activites.
thanks for u all.


likaa

1 reply

Oldest first
  1. 0
    Dayanidhi Dhandapany ·
    use global change to delete a resource, for example

    (1) (2) Data Item (3) Criteria (4) DataItem/Value
    (1)If (2) Resource (3) EQ (4) CARPENT

    number within bracket indicates the position of column in global change
    (1)then (2) RES (3)DELETE (4) CARPENT

    the above will remove resource CARPENT assigned to all activities, if you want to remove the ’Carpent’ only to certain activities you have to change the condition accordingly.

Log in or join to reply