Primavera vs Safran

Rachel Mournian (nee Walker)Member for 21 years 1 month
Created
6
2
0
Can anyone give me some examples of the benefits of Primavera over Safran? I am putting a list together for our corporate team as I’m trying to get Primavera to replace Safran and just want to make sure I haven’t missed anything.

6 replies

Oldest first
  1. 0
    Shah. HB ·
    Hi Rachel

    Safran is a scheduling software just like primavera ?
  2. 0
    Vladimir Liberzon ·
    Why do you want to replace Safran by P6?
    Do you need some functionality that is absent in Safran?
    Usually people select the software basing on their own requirements. It does not make sense to compare what you do not need. So create a list of your own requirements and then look at the capabilities of competing packages.
  3. 0
    Ian Meister ·

    do safran and primavera have

    do safran and primavera have similarities?

    on my understanding they are different.

    safran can utilize scurves while primavera dont have.

    if you have any ideas regarding comparison please feedback here.

    been using primavera 1st but now we currently using safran for planning portfolio.

  4. 0
    Muhammad Aqeel ·

    Dear Mr. Rachel    May know

    Dear Mr. Rachel
     

     

    May know how can i get Demo version of soran to check it please and later on i can go for sofran.

     

    let me advise please

  5. 0
    Steinar Dalva ·

    Hi, Just a comment to Mike

    Hi,

    Just a comment to Mike Peyton's first comment about Longest Path in Safran Project:

    The default calculation in Safran Project is "No Longest Path". This can be changed (individually for each project) to be "Longest Path". Do this under Setup>Networks>Analysis Options:

    No other scheduling software on the market have a ritchness of Scheduling options that match Safran Project.

    Steinar.

  6. 0
    Vladimir Liberzon ·

    Hi Steinar , did you study

    Hi Steinar ,

    did you study all scheduling softwares on the market?

    Best Regards,

    Vladimir

Log in or join to reply