Skip to content

cluse 14 program

Eduardo PadulMember for 21 years 3 months
Created
6
4
0

Hi to all,

What is a clause 14 program?

6 replies

Oldest first
  1. 0
    Christian Adrian De Vera ·
    Eduardo

    This is a condition clause in the contract which requires a contractor to provide his client the necessary construction/contract schedule or program.

    HTH

    Christian
  2. 0
    Deep Elias ·
    Clause 14.1

    According to FIDIC (Fourth edition 1987)The Contractor should, submit programme of works to be executed within the time stated in Part II of the Conditions (after the date of the Letter of Acceptance)to the engineer for his consent.

    it also mentions that the Contractor shall provide in writing, a general description of the arrangements and methods which the Contractor proposes to adopt for the execution of the Works.

    Regards
  3. 0
    Ponnaganti Sridhar ·
    Hi eduardo padul

    what Deep sad is excatly correct i think, and he is very keen on the clause 14 and the subclause 14.1.

    thats it, what is ment by clause 14 programme and that is going to be your baseline progamme of the project until it gets revised again

    cheers!
    Sridhar
  4. 0
    Charleston-Joseph Orbe ·
    Hi Eduardo,

    Clause 14 programme refers to FIDIC clause 14. If the contract is as per FIDIC then the submission of programme, planning, schedule will be as per clause 14.

    During the martial law years, a lot of foriegn funded project use FIDIC as form of contract between the Philippine Government and contractors, local or international.

    As years pass by, the wise guys in DPWH, tweeked PD 1594, created the blue book (FIDIC is the red book), called the book of government construction in our native land. So everything change, that is why although your are working in roads and infrastruture, you are still innocent on FIDIC.

    YOur previous generation were very well verse in FIDIC.

    Cheers,

    Joseph
  5. 0
    Ponnaganti Sridhar ·
    Hi Friends

    i would like to know more about FIDIC and its clause in detail.

    what is ment by red book , and what is blue book?

    it is becoming very diffucult to understand the clauses from RED Book , it always shows reference to some other clause in the same but may be in some other clause, is there any other way to understand get the information clearly and in a simple way

    thankyou
    P.Sridhar
  6. 0
    A D ·
    Best way to find information is:

    http://www.fidic.org/

    Anyway, Clause 14 is used as per old FIDIC

    As per FIDIC 1999, its clause 8.3

    Cheers,

    Raviraj A Bhedase

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?