copying of same activities

Vijayendra SurveMember for 19 years 5 months
Created
5
3
0
sir, i want to insert same MEP activites & link tht to civil activies for 54 floors is there any option other than storing n fragnet & then retriving on respective floor manually & linking it with civil act. which are external .pl tell me if any other way for insering same activities & then linking tht other than fragnet & copying.

5 replies

Oldest first
  1. 0
    Mangesh Khuspe ·
    hi
    considering the building is identical, first u can create all detailed activities for 1 floor, link them, schedule it.
    then select all and paste them and now link them with earlir ones. now copy this bunch and paste it again and continue this process, until u ahve finished.(thats the way i do).
    secondly there is no option other than using fragnets.
    so u will have to proceed with it.

    regards
    mangesh
  2. 0
    Vijayendra Surve ·
    thank you sir,
    i was trying in global change if optionis there but then sir this process is taking whole lot of time...so bit labourious...anyways ways thks once again..
  3. 0
    Mangesh Khuspe ·
    hi dear
    look what i do is create activities for 1 floor, then from this bunch, i create 2 floors, then copy this bunch of activities for two floors and paste them and now link this bunch with earlier one thus creating activities for 4 floors, now this 4 floors will create activities for 8 floors. in this way u can create prog for no of storeys in very less time. (but the building must be identical).

    regards
    mangesh
  4. 0
    Dave Ellis ·

    Hi   You could create a WBS

    Hi

     

    You could create a WBS branch for a floor & just copy that.

  5. 0
    Ian Dack ·

    Yes, your replies are the way

    Yes, your replies are the way out for you V, just remember to review when all are copied over then start to add your inter-relationships with each floor.

    Review, review & review again.

    good luck,

    Ian