What are the ideal checks you should carry out to check a just completed Construction Programme completed on P3/P5??

4 replies

Oldest first
  1. 0
    A D ·
    Hi Arvind,

    Check this link, Most useful. Cant get better than this!!

    http://www.ronwinterconsulting.com/rabaseline.htm

  2. 0
    Oliver Melling ·
    Arvind,

    Try checking your schedule log to see if you have any activities without relationship, or if you have unsatisfied constraints etc.
  3. 0
    Mike Morrison ·
    The

    http://www.ronwinterconsulting.com/rabaseline.htm

    link is amazing. Thank you both for asking the question and directing me to this web page.
  4. 0
    Arvind Ramaganapathy ·
    Thanks Raviraj. Thats an excellent link that covers all my doubts.