rc structures... concrete/rebar ratios

Bill TrewickMember for 22 years 7 months
Created
3
5
0
Anyone have any indicative tables showing ratios tonnes rebar to M3 concrete for rc structures... possibly showing breakdown into elements... Bases, walls, slabs, soffits. Piles etc.?

3 replies

Oldest first
  1. 0
    Armando Moriles ·
    Warehouse Type of Project:

    Isolated Footing> 80 - 120 kgs/m3
    Pedestals/Columns> 120 kgs/m3
    Beams>110 - 120 kgs/m3
    Slab on Grade> 50 kgs/m3

    Hope it helps...


    Arman
  2. 0
    Bill Trewick ·
    Thanks Armando... I managed to find some more information yesterday... from a UK Civil’s Design Group

    Specific data for "Water Retaining Structures"
    Walls 100mm thickness per metre retained height rebar density 120kg/m3
    Bases wall thickness plus 50mm rebar density 130kg/m3
    For piled bases the density increases to 150kg/m3
    General note - for non water retaining structures reduce the densities by 25%.
  3. 0
    Armando Moriles ·
    Thanks too Bill...

Log in or join to reply