ASTA Experts - help
In the Open Standard
James ThorpeMember for 21 years 1 month
- Created
- 0
- 3
0
Dear All
I tried to prepare a histogram in Power Project Version 9 by using following steps:
In Code Libraries, I established following ‘Resources’ in ‘Permanent Resources’ for steel works and decoration activities
a) Steel Fixers
b) Decorators
I tried to put Start and End dates for these resources there but could not succeed,
Please let me know that how can I put Start and End dates for these Resources in ‘Permanent Resources in Code Library’ (so that related area may shown graphically) because Start and End columns are fixed in ‘Permanent Resources in Code Library’ or
Please advise me a few important hints for assigning dates for these resources so that I may overcome this problem.
Many thanks
I tried to prepare a histogram in Power Project Version 9 by using following steps:
In Code Libraries, I established following ‘Resources’ in ‘Permanent Resources’ for steel works and decoration activities
a) Steel Fixers
b) Decorators
I tried to put Start and End dates for these resources there but could not succeed,
Please let me know that how can I put Start and End dates for these Resources in ‘Permanent Resources in Code Library’ (so that related area may shown graphically) because Start and End columns are fixed in ‘Permanent Resources in Code Library’ or
Please advise me a few important hints for assigning dates for these resources so that I may overcome this problem.
Many thanks
Replies
Oldest firstNo replies yet. Be the first to answer.
Log in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?