ASTA Experts - help

James ThorpeMember for 21 years 1 month
Created
0
3
0
Dear All

I tried to prepare a histogram in Power Project Version 9 by using following steps:


In Code Libraries, I established following ‘Resources’ in ‘Permanent Resources’ for steel works and decoration activities

a) Steel Fixers

b) Decorators


I tried to put Start and End dates for these resources there but could not succeed,


Please let me know that how can I put Start and End dates for these Resources in ‘Permanent Resources in Code Library’ (so that related area may shown graphically) because Start and End columns are fixed in ‘Permanent Resources in Code Library’ or


Please advise me a few important hints for assigning dates for these resources so that I may overcome this problem.


Many thanks

Replies

Oldest first

No replies yet. Be the first to answer.