Spun Pile Prod-Rates
In the Open Standard
Larry RinoMember for 18 years 11 months
- Created
- 2
- 2
0
I am on the process of establishing the duration for piling works with info below:
Type of Pile : Spun Pile (Concrete hollow)
Size : 600mm Diameter
Penetration depth : 40 mts.
Qty : 6,000 nos.
I appreciate any idea you can share, regarding productivity rates for driving /installation of spun pile, in:
a) man-hours per pile or
b) numbers per day per equipment.
Many thanks,
Larry R.
Type of Pile : Spun Pile (Concrete hollow)
Size : 600mm Diameter
Penetration depth : 40 mts.
Qty : 6,000 nos.
I appreciate any idea you can share, regarding productivity rates for driving /installation of spun pile, in:
a) man-hours per pile or
b) numbers per day per equipment.
Many thanks,
Larry R.
2 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?