Spun Pile Prod-Rates

Larry RinoMember for 18 years 11 months
Created
2
2
0
I am on the process of establishing the duration for piling works with info below:

Type of Pile : Spun Pile (Concrete hollow)
Size : 600mm Diameter
Penetration depth : 40 mts.
Qty : 6,000 nos.

I appreciate any idea you can share, regarding productivity rates for driving /installation of spun pile, in:
a) man-hours per pile or
b) numbers per day per equipment.

Many thanks,
Larry R.

2 replies

Oldest first
  1. 0
    Larry Rino ·
    Clive,

    The pile joints will be welded, however, I would appreciate if you can share your production data for both type of jointing (if available). I look forward to your direct response. TYs.

    Larry
  2. 0
    Larry Rino ·
    Clive,

    I appreciate the information you gave to me, namely "10 rigs 6000 piles about 3 to 4 months". This then would equate to approx. 6-8 piles (40M) piles per day per rig. Ill consider all other factors that would affect the productivity.

    Thanks,
    Larry