P5 to P3 Converstion

Brian BeckMember for 19 years 1 month
Created
4
2
0
When I export from P5 to P3, I’m getting negative lag on my longer duration activities?

Anyone experience this problme?

4 replies

Oldest first
  1. 0
    Dieter Wambach ·
    Brian
    Negative lag is on the relationships. Which kinds of relationships are involved? How was the lag before?
    If the float becomes negative you can check the calendars.
    Cheers
    Dieter
  2. 0
    Brian Beck ·
    I got it fixed.

    Has to do with un-checking the Primary Resourse box on each item under the Resources tab on the Activity View.

    Did a global change to effect all activities.
  3. 0
    Noha Attya ·
    hi all planners
    the site for downloading the P5 manual is not working or damaged
    if any one know another like
    please advise
  4. 0
    Mohamed Edris ·
    Hi all,

    Whenever i am exporting a schedule from P3 to P5 , i got negative float in P5 however there was no negative float in P3 for the same schedule.

    Pls advise.

    Thanks
    Mohd