Oldest first- 0GCGie Chris Rimando ·Hi to All,
I’m also currently doing Cost Analysis ,i would greatly appreciate if i can get a copy of Earned value analysis and Earned value measurement.
May I have a copy of progress monitoring system on based physical progress for Petrochemical or oil & gas projects.
Thanks.....
- 0RCR. Catalan ·Ian Couser,
You don’t need Excel, P3 has the capability to do EVA.
BCWS or Planned Value (Budget)
If your baseline schedule is cost-loaded you can run it to get BCWS whether you want it weekly or monthly.
BCWP or Earned Value:
P3 calculates this as your current % complete x budget of an activity. You can also use UDF and use global change to get the cost per activity.
ACWP or Actual Cost:
This is actual cost and manually logged in P3. These are cost coming from your Subcon Invoices, salaries, POs to Suppliers.
SV or Schedule Variance = BCWP-BCWS
CV or Cost Variance = BCWP-ACWP
From above you can get SPIs & CPIs.
Hope the above will help.
R. Catalan