Project Management Software - Replacement for InControl
In the Open Standard
Steve LindsayMember for 20 years 3 months
- Created
- 3
- 4
0
We are an Oil and Gas Engineering Consultancy and currently use InControl by Worley Parsons for in-house engineering planning, budget, progress control & reporting and document control. Worley Parsons has recently taken the decision to withdraw external suppport for InControl. In the short term we have no option but to contiue using it but need to source a replacement incase of system failure, which would leave us of the proverbial creek without a paddle.
System overview InControl is built up of a number of modules using a file sharing system.
Primarily this gives us:
Proposal Generator: CTR sheets with scope, inputs deliverables man-hours and costs etc, barchart, histogram and a number of tabular reports.
Project Control: All of the above with the addition of actual and earned man-hours and more reports. progress is generated via the deliverables module by creating predefined progress gates linked to issue status automatically updated when a transmittal is generated
Deliverable Control: Engineering and Venfor deliverable control - revision history, transmittal history, expediting and MDR reports.
There is much more besides the brief description given above.
Does anyone know of a similar system which I can review as a possible replacement.
System overview InControl is built up of a number of modules using a file sharing system.
Primarily this gives us:
Proposal Generator: CTR sheets with scope, inputs deliverables man-hours and costs etc, barchart, histogram and a number of tabular reports.
Project Control: All of the above with the addition of actual and earned man-hours and more reports. progress is generated via the deliverables module by creating predefined progress gates linked to issue status automatically updated when a transmittal is generated
Deliverable Control: Engineering and Venfor deliverable control - revision history, transmittal history, expediting and MDR reports.
There is much more besides the brief description given above.
Does anyone know of a similar system which I can review as a possible replacement.
3 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?