Dear Planner,

How to prepare a program starting from scratch..

Thanks

Mout.

2 replies

Oldest first
  1. 0
    Abhijit Kale ·
    by logical thinking and making logical relationships.

    Please take a look at the contract,
    first understand the project completely, to know the project duration, contract value, contractual obligationsn mile stones, to know the technical specification, and last but not the least major quantities.

    Once u get the idea abt the project, break the project sectorwise n in diff subsectors. split the activities in to sub activities and corealte with respect to thr duration.
    First prepare the work plan then start with the program.

    Cheers,
    Abhi
  2. 0
    Konstantinos Parsalidis ·
    In M&E services,

    1) you start by looking at the drawings,
    2) then go through the scope of works, then you start looking at the Main Contractor’s programme,
    3) then discuss with the project manager and
    4) you start drafting a (design, procurement, drawings production, construction, commissioning) programme.
    6) You then take it back to your project manager, go through it and implement their comments.

    Simple! ;)