Key milestone in clause 14 not realistic

Kier LegardMember for 20 years 2 months
Created
1
3
0

Hi to all,

I prepared a clause 14 programme and found that some key milestone dates are not realistic(2 months behind) due to procurement activities.We submitted the Cluse 14 programme to consultant and gave us instruction to compressed all works to meet the milestone date.Clients also advised us to make claim on the delays after approval of clause 14.

Please advice

regards,
kier


1 reply

Oldest first
  1. 0
    David Wallace ·
    Kier,

    Did you agree to the milestones prior to the submission of the Clause 14.1? If not, have they been introduced since the submission but prior to the consent for use?

    Also, did the Engineer Instruct you to Accelerate the works? (Please note the two key words ’Instruct’ and ’Accelerate’)

    I’m a litte amused that the Client has advised you to submit a claim, sounds a bit like a set-up to me.

    Can you give me a wee bit more info?

    Cheers,

    Davie.