Key milestone in clause 14 not realistic
In the Open Standard
Kier LegardMember for 20 years 2 months
- Created
- 1
- 3
0
Hi to all,
I prepared a clause 14 programme and found that some key milestone dates are not realistic(2 months behind) due to procurement activities.We submitted the Cluse 14 programme to consultant and gave us instruction to compressed all works to meet the milestone date.Clients also advised us to make claim on the delays after approval of clause 14.
Please advice
regards,
kier