editing actual date

Nar ThapMember for 19 years 1 month
Created
2
4
0
experienced a typical, never happened problem in suretrak. alredy completed activity with actuals on both ES & EF. Now it is realised that the activity has not completed yet so I put 5d Rem Duration and wanted to change EF accordingly. Surprisingly, the EF everytime stayed at DD and the bar is not extending beyond DD. All auto cost rules are ticked. Anybody can give me the solution?

2 replies

Oldest first
  1. 0
    Shahzad Sikandar ·
    what was the original duration ?
    check actual duration / units are zero

    and also percnet complete should be zero.

    then put remaining days,

    try this

    might work

    cheers
  2. 0
    Nar Thap ·
    Sikandar,
    did not worked yet. found where was the problem and able to solve it. The reason behind was the already driven resorce.Thanks for your suggestion anyway.