Hi.All

Any one advise me how to controll all activity by activity ID.

i am using P3 i have some Activity which is not starting / finishing in order.

in that i sort my all activity by Activity ID

while i am closing my file.and open againg all activity in disorder.

Thanks for your Valuable advise

Shahzad

2 replies

Oldest first
  1. 0
    Shahzad Sikandar ·
    shahzad

    when you it by activiry ID, make sure you save the layout, if you want to keep this layout features intact.

    then when you open it next time, it should all be ok.

    hope it helps

    cheers
  2. 0
    Shahzad Sikandar ·
    when you sort it by activiry ID, make sure you save the layout, if you want to keep this layout features intact.

    then when you open it next time, it should all be ok.

    hope it helps

    cheers