Hello,

I am about to start a contract job in the UK as a project planner, but the company have requested me to provide a professional indemnity insurance to cover the cost of any possible future claims against me due to my mistakes / omissions.
Is this the general practice in the UK? Do usually companies require such insurance for contract planners?
I would appreciate your comments.

Thank you.

2 replies

Oldest first
  1. 0
    Tarek Barham ·
    Dear J J.

    It is very strange, Im worrking in planning and cost control since 8 years ago, and no company asked me bofre for this kind of insurance.

    Although Im working now with 3 Billion USD project , but still no body asked this king of things.

  2. 0
    Brian Fletcher ·
    Yes generally most of the agencies I have worked through request this. It is fairly hard to track down companies that specifically cover Planners or Planning Engineers. I used a company called Insurance2day for my PI and my employers & public Liability Insurance and they seem ok.

    You will need to call them rather than get a standard policy to explain exactly what you are doing. If you are mainly office based rather than out on site doing work I would mention this as soon as you mention construction sites to Insurance they see £ signs!!