P6 WBS Help

Andy PetkusMember for 23 years 11 months
Created
6
2
0
Hi everybody

I need some help please. I’m a new user in P6 and I need to move/copy a WBS structure from one project to another and I also need to delete the existing WBS structure in the target project.

I’ve copied my new WBS over no problem, but I cannot delete the original structure as I’m getting duplicate activities because of the 2 structures.

Any ideas?

Thanks

6 replies

Oldest first
  1. 0
    Richard Day ·
    Andy,

    How did you copy over the WBS?

    Thanks
  2. 0
    Shahzad Sikandar ·
    when copying WBS

    you get

    copy WBS Options, dont you?

    uncheck activities box
    and the activities wouldnt be copied, only WBS will be copied, so you end up with no duplication.

    cheers
  3. 0
    Andy Petkus ·
    Thanks guys,

    Richard, I just copied and pasted but couldn’t delete/overwrite the original WBS structure.

    Shazad,I tried that also, but still couldn’t delete the orginal WBS.

    What I need to do is to take my WBS and the activities which I have coded/allocated with the WBS code I want and overwrite the target programme so that it shows my WBS structure and that all the target activities show my WBS codes.

    I’ve gone upside down and inside out trying all sorts things within P6 to do this - can’t do it or rather I don’t know how to do it.

    I’m beginning to think that I might have to export both my programme data and the target programme data into say, Excel or Access, combine and manipulate the date to what I want and then import back into my target programme.

    I don’t know if this can be done or not in P6.

    Obviously, I don’t to have to start from the beginning again in recoding the target programme if I can help it, (about 7500 activities).

    Anyway ideas/help would be great, thanks.


  4. 0
    Shahzad Sikandar ·
    if you need to delete WBS structure in target/baseline programme, then detach the baseline and open it then delete whatever you want to delete.

    it shouldnt be too difficult.

    hope this helps

    thanks
  5. 0
    Andy Petkus ·
    Shazad,

    That’s my problem also. I cannot seem to be able to delete the target WBS structure. When I right click on the parent node, the delete button is greyed out.

    I think maybe this is due to the activities still being allocated to it.

    Thanks

    Andy
  6. 0
    Abu Lana ·
    Hi all
    Could you try to creat a new blank document and merge down the WBS u want.
    pick from original whatever you want, and from target also, combine them manualy in the new blank project. i worked fine in P3 versions and i tried it in p5 it worked also.