CSI for Pre-construction and Post-construction stages

Yasser ElyosefiMember for 21 years 6 months
Created
5
2
0
Hello Planner,

CSI Master format is mainly built for Construction stage.

Is there CSI codes to define Pre-Construction activities, such as Consultants selection and appointment, Evaluation and Award, Eng. and Design (Concept, Schematic, DD, CD) , Tendering, Bidding and Award process, Procurement (of contractors), Procurement (of Materials and Equipments ), etc.... as well as Post-construction stage such as testing, commissioning, handing over, snagging, liabilities, etc…

Regards,

Yasser

5 replies

Oldest first
  1. 0
    Yasser Elyosefi ·
    Hello Planners,

    What is up?

    I didn’t receive any single response from any of you for my question below.

    Is the question is too easy or too difficult?

    Yasser
  2. 0
    Rami Al Haddad ·
    hi,,, depending on the format you are using which i suppose is the 1995 format, look in Div 00!

    regards,
    rami
  3. 0
    Ronald Romero ·
    Hi Yasser,

    Your dillema is the same as mine since i’m working with a project management company. I use the procurement and contracting requirement from div 00 as a preconstruction Division. I don’t use any division for post contruction because i usually put there testing and commissioning, snagging and demobilization and the rest of the division fall within the construction stages.

    Hope this helps you a little bit.

  4. 0
    Yasser Elyosefi ·
    Hi Rami, Ronald,

    I’m using CSI Master Format 2004 in which Div 00 is not there. The first division is 01.

    Regards,
  5. 0
    Ronald Romero ·
    Yasser ,

    download the CSI on this page http://www.csinet.org/s_csi/docs/9400/9361.pdf

    Cheers and Keep on planning