Skip to content

Activities locked.

Bailay BasuMember for 18 years 11 months
Created
3
6
0
I am new planning engineer and I have project schedule with two sub projects for JV project. I would like to change some orginal duration to rectify the TF as per management instruction. But some activities showing that," Activity currently locked by another user" and I am not able to modified anything on it.
Can somebody advise me how to recitified this issue and modified the orginal duration.

3 replies

Oldest first
  1. 0
    Arnold Puy ·
    Hi Bailay,

    The reason why you cannot modify it is because you do not have access to your current project and was restricted by the owner or user. I guess you are using P3x if so, try the following steps:

    1. Close your Current Project including Primavera Window.
    2. Go to Start -> Programs -> Primavera and select Netset.
    3. Type password "netset".
    4. From Primavera Network Administration, Select Option
    5. Then Select Change Project Owner.
    6. Under the Projects, search the project you wanted to change.
    7. After selecting your project, change the Owner to P3 then close and exit.


    Regards,

    Arnold
  2. 0
    Bailay Basu ·
    Thanks arnold. I follow your advice and all activities are working well.
    But now i am facing other problem in same schedule that, i am try to prepare s- curve through by Graphic report and it’s Showing " Error in RECMGR - status 2"
    Can you advice me how to rectify this issue and i am waiting for your reply

    Regrads,
    Bailay.
  3. 0
    Smiling Shagger ·
    namaste
    it means that you are using a pirated copy of P3

    Peace, hempfully,
    smilingshagger

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?