Skip to content

Relationship lines

Hengki Amri RozaMember for 18 years 3 months
Created
1
5
0
Dear planners,

I have a problem with relationship lines when I push F9 in my P5 schedule. The relationship lines didn’t follow the updated schedule but still at the baseline.

Anyone can tell me what is the wrong setting in my P5?

Regards,
Hengki

1 reply

Oldest first
  1. 0
    Arnold Puy ·
    Hi Hengki,

    In View Menu --> Bars, move the Baseline Bars below the Current & Remain Bars by using “Shift up” & "Shift down” buttons.

    HTH.

    Arnold

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?