Planned Value in P6
In the Open Standard
Henry LeonMember for 19 years
- Created
- 0
- 2
0
I enter Planned Budget unit manually in my schedule, but when i show the column "Planned Value unit" show wrong number, however in Resource spreadsheet show the right number.
This only happend to enter manually the budget units, because when i use resource curve all is ok.
This only happend to enter manually the budget units, because when i use resource curve all is ok.
Replies
Oldest firstNo replies yet. Be the first to answer.
Log in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?