mep sequence in building

Johnny WeeMember for 19 years 2 months
Created
1
2
0
just share your ideas,need to complete the following:

electrical
wall:
after blockwork chasing/marking,we can start for conduiting and g.i. box and db box then close by plaster.. then we install wiring for light and power..then install/terminate db after light fittings

ceiling:
after blockwork, install hangers then g.i. tray then high level wiring install, then access for ceiling works

a/c

after blockwork, we can start for 1st fix a/c hanger then start ducting / insulation and fcu and chilled pipes installation in parallel, then connect line bet fcu and duct,then access for ceiling works

after fixing of pipes, testing/commission

1 reply

Oldest first
  1. 0
    Samer Zawaydeh ·
    Dear Johnney,

    It depends on the size of project that you have. Either go by

    1st fix electrical: Walls, ceiling and Floor
    2nd fix electrical: pulling cables and wires,
    3rd fix electrical: sockets, cover plates, lighting fixtures and commissioning.

    1st fix Mechanical
    2nd fix Mechanical
    3rd fix Mechanical: installing fixtures, pads and commissioning,

    for big size project, it is preferred that you go by system. For MEP, it can run between 15-25 systems.

    Let me know if you have a more specific question.

    Best,

    Samer

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?