Using the Contingency reserve
In the Open Standard
Sam OnumahMember for 18 years 5 months
- Created
- 4
- 3
0
After spreading the manhours among the various work packages I was still left with some reserve manhours which I kept in the contingency reserve.
I linked the predecessor of the reserve to the start milestone of the one of the work packages and the successor to the finish milestone of the project.
In this case when the work packages are being progressed the is also being progressed.
I am wondering if this is the right way to do it.
I linked the predecessor of the reserve to the start milestone of the one of the work packages and the successor to the finish milestone of the project.
In this case when the work packages are being progressed the is also being progressed.
I am wondering if this is the right way to do it.
4 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?