Consolidating Primavera and MSP plans
In the Open Standard
Oliver MellingMember for 19 years 5 months
- Created
- 14
- 5
0
PPlanet,
As a main contractor using Primavera (which forces actual performance into the past and remaining work into the future as a rule) i find integrating sub-contractors MSP plans extremely time consuming.
Unfortunately, most of the time i receive MSP plans that have been updated by percentage only and have unfinished tasks in the past and completed ones in the future.
Is the main contractor entitled to ask the sub to re-visit there plan and align the method of updating progress? and more importantly is the use of drop lines to show tasks ahead/behind of schedule still a valid method of tracking progress?
As a main contractor using Primavera (which forces actual performance into the past and remaining work into the future as a rule) i find integrating sub-contractors MSP plans extremely time consuming.
Unfortunately, most of the time i receive MSP plans that have been updated by percentage only and have unfinished tasks in the past and completed ones in the future.
Is the main contractor entitled to ask the sub to re-visit there plan and align the method of updating progress? and more importantly is the use of drop lines to show tasks ahead/behind of schedule still a valid method of tracking progress?
14 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?