Resource Original Lag
In the Open Standard
Ahmed ElkordyMember for 17 years 11 months
- Created
- 11
- 2
0
Hello
I have a question and I hope i get help.
I have an activity, which is FCU supply..the payment condition for its delivery is 25% down payment and 75% after one month from delivery, means i need to expand resource usage one month AFTER the activity has finished.
Any help? I’m using P6.
What i did was divide the two payments into two resources, one with a curve that is 100% front loaded and budgeted quantity of 0.25 units, and the other 100% back loaded and with a budgeted quantity of 0.75 units but when I set original lag to 1 month for the 2nd resource, the activity finish date is delayed by 1 month too, which i don’t want to happen.
Please share your advice
thank you
I have a question and I hope i get help.
I have an activity, which is FCU supply..the payment condition for its delivery is 25% down payment and 75% after one month from delivery, means i need to expand resource usage one month AFTER the activity has finished.
Any help? I’m using P6.
What i did was divide the two payments into two resources, one with a curve that is 100% front loaded and budgeted quantity of 0.25 units, and the other 100% back loaded and with a budgeted quantity of 0.75 units but when I set original lag to 1 month for the 2nd resource, the activity finish date is delayed by 1 month too, which i don’t want to happen.
Please share your advice
thank you
11 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?