Skip to content

Power Transmission Line Programme

Mohsen MMember for 18 years 7 months
Created
4
5
0
Dear All,

I am about to develop an electricity transmission line programme. I have to break Design, Procurement, and construction works into details. Does anyone can help me about required activities, duration and sequencing?

Regards,

Mohsen

4 replies

Oldest first
  1. 0
    Trevor Rabey ·
    Surely, it is the other people in your own company, the ones who know how it can be done, and who know all of the specific circumstances, and who have committed to doing it, who are best placed to help you?
  2. 0
    Mohsen M ·
    Hi Trevor,

    Thanks for your reply.

    I would not post a note at Planning Planet if I could find help from the Company that I work in.

    Regards,

    Mohsen
  3. 0
    Trevor Rabey ·
    If you say so, but how is it possible that your company has a contract to do something they don’t know how to do?

    I can help you, but not without any information about the project, and right now I don’t know anything about it.
    When to Start?
    When to finish?
    What terrain?
    How many km?
    How many pylons?
    What Volts?
  4. 0
    Samer Zawaydeh ·
    Dear Mohsen,

    I would suggest the following:

    1. Review all the Contract documents that you have. If you have a BOQ, start with that.

    2. Sit with the Engineer Manager that you have.
    a. You will need to submit a Technical Design calculation report that must be approved by the client.
    b. Testing might be requested. So you need to submit the testing facilities that you want to test at, and get it approved.
    c. You will need to Fabricate, Galvanize and Ship the Prototype and test it. After approval you can start production.
    d. After approval of the Prototype, you can complete the "detail drawings".
    e. Engineering will Create the BOQ.

    3. Once the BOQ is created. You will need to sit down with the Procurement Manager. And determine the following
    a. Plates Supplier, and Estimated Time of Arrival (ETA)
    b. Angles ETA.
    c. Bolts ETA.
    d. Electrical components ETA.
    e. Supplier of the Civil works if it is done by another party. Or you will need to have another section for the Construction section

    3. Construction
    a. Fabrication
    b. Galvanization
    c. Shipping to location
    e. Civil Works
    f. Construction
    g. Handing Over


    If you need any more details, I might be able to assist.

    Best ,

    Samer

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?