Dears,
Have anybody find a definition for this terminology,, (( Unsatisfied Constraints)) appears when viewing schedule log in P6 ?

Please advice.

3 replies

Oldest first
  1. 0
    Arnold Puy ·
    Hi Mohammed,

    Unsatisfied Constraint occur only if your activity has a constraint assigned "Start on", "Start on or Before" & "Mandatory Start" later than the assigned date.

    Say for example:
    You assigned constraint to your activity that starts on 04-Dec-08 however, your actual start is on 06-Dec-08. This is the unsatisfied constraint.

    HTH.

    Regards,

    Arnold
  2. 0
    Mohammed Abo El Magd ·
    Hi Arnold,
    This is very good. Thanks. Have you find it in the help ??

    Regards
  3. 0
    Arnold Puy ·
    Hi Mohammed,

    You’re welcome. No, I didn’t find it in HELP. I read in one of many articles as well as, it so happen that it’s part of my experienced and I tried to experiment using all types of constraints.

    Thanks.

    Arnold