What is the difference between an EPC schedule of a project & Engg, Procurement & construction schedules as separate entity? Do we really need to merge them to make single EPC schedule?

2 replies

Oldest first
  1. 0
    Dieter Wambach ·
    Abhishek

    You’ll have to plan and to control the relationships between the different phases - you can’t erect a turbine before its foundation is ready, you’ll have to create the requisition before order, regard arrival at site before erection, etc.
    If you’ll plan with different inter-linked schedules or use one single schedule depends on project, its stakeholders (e.g. a required data exchange with a subcontractor) and the features of the software you use.
    The output should be the same.

    Have a happy new year!

    Dieter
  2. 0
    Samer Zawaydeh ·
    Dear Abhishek,

    A Program of Works is prepared to make sure that the project "scope" is complete on "time and within "cost".

    Your job as a planned is to prepare such a Schedule. The project type determined what activities you need to include; Sales, Estimation, Design, Detailing, Procurement, Storage, Logistics, Construction, Fabrication, Erection, Quality Control, Tre v

    atment, Commissioning, and many more.

    Best Regards,

    Samer