Engineering, Procurement & Construction S-Curve
In the Open Standard
Amr DiabMember for 19 years 8 months
- Created
- 6
- 2
0
In an EPC project, it is requested to prepare the following:
1. Overall Project S-Curve
2. Engineering S-Curve
3. Procurement S-Curve
4. Construction S-Curve
To calculate the construction progress I used the manhours allocated for each task then I generate the S-Curve.
The question is: for the Engineering and Procurement should I allocate manhours in order to be similar as the construction then produce Overall Project S-Curve?
If so, can anybody know manhour rates for the engineering and procurement activities?!!
Regards,
Amr
1. Overall Project S-Curve
2. Engineering S-Curve
3. Procurement S-Curve
4. Construction S-Curve
To calculate the construction progress I used the manhours allocated for each task then I generate the S-Curve.
The question is: for the Engineering and Procurement should I allocate manhours in order to be similar as the construction then produce Overall Project S-Curve?
If so, can anybody know manhour rates for the engineering and procurement activities?!!
Regards,
Amr
6 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?