WBS Orig. Budget Vs. WBS Activities Roll-up Sum. Budget
In the Open Standard
Steve OgradyMember for 17 years 10 months
- Created
- 13
- 2
0
I currently have a schedule that is resource loaded. I have entered the ‘Original Budget’ into to each and every WBS (which mimics the pay items on the contractor’s submitted invoice). I have also resource loaded each and every activity (budgeted units/cost etc ;).
I am wondering how this are related from a cost point of view. I thought the budgeted cost for each WBS should equal the summary roll-up cost for activities under that specific WBS. This does not appear to be the case (maybe I am not showing the correct Columns?)
Example
1.0 WBS $500,000
1.01 Act 1 250,000
1.02 Act 2 100,000
1.03 Act 3 650,000
Any assistance is much appreciated.
Thanks
I am wondering how this are related from a cost point of view. I thought the budgeted cost for each WBS should equal the summary roll-up cost for activities under that specific WBS. This does not appear to be the case (maybe I am not showing the correct Columns?)
Example
1.0 WBS $500,000
1.01 Act 1 250,000
1.02 Act 2 100,000
1.03 Act 3 650,000
Any assistance is much appreciated.
Thanks
13 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?