Duration Type/% complete type
In the Open Standard
Catherine BarthelemyMember for 18 years 4 months
- Created
- 5
- 2
0
hello everyone! I have an issue which I think is to do with my settings, but having tried different options unsuccessfully, so here I am to pick your brains;
I have an activity with budgeted units (120) 04/1/08 till 23/02/09. 75% complete, Data Date 16/01/09.When producing units per month report, I have 104 units in dec 08 and 16 in Jan. I have tried changing the settings, and the resource curve type but P5 does not seem to spread the resources up to the end date.
Any ideas?
I have an activity with budgeted units (120) 04/1/08 till 23/02/09. 75% complete, Data Date 16/01/09.When producing units per month report, I have 104 units in dec 08 and 16 in Jan. I have tried changing the settings, and the resource curve type but P5 does not seem to spread the resources up to the end date.
Any ideas?
5 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?