Level Of Effort Activities
In the Open Standard
Catherine BarthelemyMember for 18 years 4 months
- Created
- 8
- 2
0
When creating a baseline programme, using LOE is quite helpful (project mgt , site supervision etc), however when progressing the plan, the logic always comes in the way, ie: if you have a SS and FF from a LOE to a normal Activity which should have started but not yet started, the LOE retains the SS/FF logic and does not allow you to claim against it. Is th
Is there an easy way to handle that rather than changing the logic, do you people recommend using LOEs in a live plan, or do you stay well clear like I used to (but I am getting forced down that road!!).And what settings do you use(Duration type etc)? Looking forward to your answers........
Is there an easy way to handle that rather than changing the logic, do you people recommend using LOEs in a live plan, or do you stay well clear like I used to (but I am getting forced down that road!!).And what settings do you use(Duration type etc)? Looking forward to your answers........
8 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?