Duration Vs. Effort and displaying on GANTT
In the Open Standard
Neal ShahMember for 17 years 7 months
- Created
- 0
- 2
0
Hello,
This is my first post so thanks in advance for viewing and responding!
I have a project, broken down into subprojects and associated tasks - I am using MS Project 2007.
One task takes 16 hours to do if 1 person did it, however the duration to actually complete would be 2 weeks for example.
How do I show this, while incorporating multiple resources and resource utlizations, like Resource A will work 10% of a full day for 2 weeks, and Resource B will work the remaing to complete the task in 2 weeks?
Thanks!
Neal
This is my first post so thanks in advance for viewing and responding!
I have a project, broken down into subprojects and associated tasks - I am using MS Project 2007.
One task takes 16 hours to do if 1 person did it, however the duration to actually complete would be 2 weeks for example.
How do I show this, while incorporating multiple resources and resource utlizations, like Resource A will work 10% of a full day for 2 weeks, and Resource B will work the remaing to complete the task in 2 weeks?
Thanks!
Neal
Replies
Oldest firstNo replies yet. Be the first to answer.
Log in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?