Duration Vs. Effort and displaying on GANTT

Neal ShahMember for 17 years 7 months
Created
0
2
0
Hello,

This is my first post so thanks in advance for viewing and responding!


I have a project, broken down into subprojects and associated tasks - I am using MS Project 2007.

One task takes 16 hours to do if 1 person did it, however the duration to actually complete would be 2 weeks for example.

How do I show this, while incorporating multiple resources and resource utlizations, like Resource A will work 10% of a full day for 2 weeks, and Resource B will work the remaing to complete the task in 2 weeks?

Thanks!

Neal