UPDATED FINISH MILESTONE?

Marwan IbrahimMember for 18 years 4 months
Created
6
1
0
Our contractor updated a finish milestone, cost loaded, to reflect a certain percentage of accomplishment. I see this wrong. Comments please.

6 replies

Oldest first
  1. 0
    Arnold Puy ·
    Hi Marwan,

    If I understood you, a Finish Milestone cannot be loaded with resources because, it is zero duration.

    Regards,

    Arnold

  2. 0
    Marwan Ibrahim ·
    Finish Milestone can be loaded, specifically with cost, which is acceptable for me or by others. The inappropriate thing that the contractor did is updating in less than 100% or updating it at certain percentages only. That is why I see that wrong.
  3. 0
    Arnold Puy ·

    I don’t think so.

  4. 0
    Marwan Ibrahim ·
    I respect ur views Arnold. Maybe we have to wait for other’s comments.
  5. 0
    Arnold Puy ·

    Finish Milestone may have a primary resource and expenses associated with it, but cannot have a resource assignments, role assignments, or time-based costs such as labor.
  6. 0
    Marwan Ibrahim ·
    Arnold, that is a great comment! I needed that... "Finish Milestone should not have a time-based cost/expense."

    Cheers!