How to assign Activity Code in P6 - Pls help

Suraya Hani HussinMember for 20 years 8 months
Created
5
3
0
Dear All,

I want to used activity code instead of WBS, so I need a favour if anyone out there can show me the correct steps how to assign activity code in new project.

Thanx.

5 replies

Oldest first
  1. 0
    Marwan Ibrahim ·
    Do you know how to make activity codes now in P6?
  2. 0
    Suraya Hani Hussin ·
    Hi..

    I tried already. I choose Enterprise -> Activity Code -> Modify. Then assign a code and value.

    Then from here i choose project -> activities -> select activity to which i assign a code and value..

    Then.. im stuck... :(
    I’ll try to do as p3. to organized. But here.. i cant find the way...
  3. 0
    Ferdinand U. ·
    View --> Group Sort --> Customize

    This Should be in P6 Forum
  4. 0
    R. Catalan ·
    Suraya,

    Dieter’s Post # 2 on the following link is helpful.

    http://www.planningplanet.com/forum/forum_post.asp?fid=1&Cat=5&Top=57675

    Regards,
    R. Catalan
  5. 0
    Suraya Hani Hussin ·
    :) Thanx a lot!!