Problem With Dangling Activities According 2 Dr. Hulett
In the Open Standard
Jose RamirezMember for 18 years 1 month
- Created
- 1
- 1
0
Problem With Dangling Activities According 2 Dr. Hulett:
I am just wondering if this is alright CPM method
Design (A30001) SS w/DEMO (A30201) can you add this to solve the Dangling Activity Issue.
**Design FF w/DEMO
I need Design to Start With Demo and Demo Must Finish With Design.
ID Predecessor Driving Rel. Lag
A30001 A30101 TRUE SS 0
A30201 A30001 FALSE SS 0
A30201 A30001 TRUE FF 0
A30201 A30101 FALSE FS 0
A30301 A30201 TRUE FS 0
A30401 A30301 TRUE FS 0
A30501 A30001 TRUE SS 0
A30501 A30401 FALSE FF 0
ID Successor Driving Rel. Lag
A30001 A30201 FALSE SS 0
A30001 A30201 TRUE FF 0
A30001 A30501 TRUE SS 0
A30101 A30001 TRUE SS 0
A30101 A30201 FALSE FS 0
A30201 A30301 TRUE FS 0
A30301 A30401 TRUE FS 0
A30401 A30501 FALSE FF 0

I am just wondering if this is alright CPM method
Design (A30001) SS w/DEMO (A30201) can you add this to solve the Dangling Activity Issue.
**Design FF w/DEMO
I need Design to Start With Demo and Demo Must Finish With Design.
ID Predecessor Driving Rel. Lag
A30001 A30101 TRUE SS 0
A30201 A30001 FALSE SS 0
A30201 A30001 TRUE FF 0
A30201 A30101 FALSE FS 0
A30301 A30201 TRUE FS 0
A30401 A30301 TRUE FS 0
A30501 A30001 TRUE SS 0
A30501 A30401 FALSE FF 0
ID Successor Driving Rel. Lag
A30001 A30201 FALSE SS 0
A30001 A30201 TRUE FF 0
A30001 A30501 TRUE SS 0
A30101 A30001 TRUE SS 0
A30101 A30201 FALSE FS 0
A30201 A30301 TRUE FS 0
A30301 A30401 TRUE FS 0
A30401 A30501 FALSE FF 0

1 reply
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?