Skip to content

ALUMINIUM CLADDING/GLAZING ACTIVITIES

Johnny WeeMember for 19 years 2 months
Created
20
5
0
Can somebody provide breakdown of activities for Aluminium Cladding and Curtain Wall Works?

20 replies

Oldest first
  1. 0
    Mike Testro ·
    Hi Johnny

    There are so many different types of installation available for cladding systems that a single simple answer is not possible.

    Can you be more specific as to what system you are using.

    Best regards

    Mike Testro
  2. 0
    Samer Zawaydeh ·
    Dear Johnny,

    This is the basic sequence of activities. I hope that the information helps. And if you have any specific question, please ask.

    1. Material submittals; Glass, Sections, Accessories, Mastic, cap plates, brackets.
    2. Site Measurements & Layout
    3. Calculation submittal and approval (Mullions, Transons, Glass) Strength and deflection.
    4. Shop drawings submittal and approval.
    5. Mock-up installation and approval.
    6. Fabrication
    7. Painting and insulation of concrete elements.
    8. Installation of Brackets.
    9. Installation of Mullions
    10. Installation of Transoms & alignment acceptance.
    11. Installation of Glass Panels.
    12. Installation of Doors and Windows
    13. Tightening of all brackets.
    14. Installation of Mastic and accessories.
    15. Testing, if required.
    16. Installation of Flashing from inside.
    17. Installation of sound insulation between floors.
    18. Installation of sound insulation between rooms.
    19. Submitting "As Built" drawings.
    20. Cleaning and handing over.

    With kind regards,

    Samer
  3. 0
    Mike Testro ·
    Hi Samer

    Another brilliant list but we need to consider the interface with the structure.

    Some systems require that the top level is reached before the brackets can be lined and leveled.

    Others allow the brackets to creep up three storeys below followed by the cladding.

    Sometimes there is more than one testing operation at different stages.

    We have the makings of a good team here.

    The best advice for Johnny is to get a method statement from the cladding contractor and follow that.

    Best regards

    Mike Testro
  4. 0
    Johnny Wee ·
    Thanks for magnificent advices from you guys.

    before, i only use a few activities:

    0)brackets fixing & leveling

    1)waterproofing on surfaces

    2)frames installation

    3)cladding panel installation

    4)sealant application
  5. 0
    Samer Zawaydeh ·
    Dear Mike,

    Thank you for your kind words. We hope that Johnny can make the best out of the information.

    Dear Johnny,

    If you give us more details about the project and the systems that you are using, we can assist more in compiling the list of activities for your use.

    With kind regards,

    Samer
  6. 0
    Prasad Ramanathan ·
    Can any body advice steps involved in spider & Fin Cladding
  7. 0
    Samer Zawaydeh ·
    Dear Prasad,

    Can you give us a small description of the project. It depends on the size and complexity.

    The basic steps should be the same:

    1. Survery- setting out.
    2. Bracket installation / Spider
    3. Fin Installation / Glass fitup
    4. Touch up
    5. Inspection and handing over.

    With kind regards,

    Samer
  8. 0
    Prasad Ramanathan ·
    Hai Samer,

    Thank you Very mich for the Information.The Project is a Multipurpose Tower which includes Cable net type dot point cladding,Spider cladding,Fin cladding,Stick & Unitized System etc.Can u pls advice the steps involved in dot point system cladding also.


    Thanks & Regards
    Prasad Ramanathan
  9. 0
    Samer Zawaydeh ·
    Dear Prasad,

    I have not done a full cladding system like the one that you described. But I would recommend that you sit down with the installer and determine the steps that they will take to complete the installation.

    Basically, these are the general steps:

    1. Survey for all the elevations.
    2. Submit survey for supervising engineer approval
    3. Shop drawings preparation
    4. Shop drawings approval
    5. Material ordering
    6. Material manufacturing
    7. Material dispatch to site
    8. Installation of Brackets/spiders
    9. Installation of Mullions
    10. Bracing installation
    11. Glass installation
    12. Mastic and touch up
    13. Inpection and handing over

    You will need to repeat steps 8-13 for all floors.

    With kind regards,

    Samer

  10. 0
    Prasad Ramanathan ·
    Hai Samer,


    Thank u .It Really helps me .But can u explain me the steps for each system seperately.

    Thanks & regards
    Prasad Ramanathan
  11. 0
    Lucas l ·
    Hi,

    I do have experience doing curtain walling, in fact currently I am serving a curtain walling contractor.

    If anyone wish to discuss on this matter or share infor, plz email me.

    I am trying to improve the schedule to service my client better
  12. 0
    Samer Zawaydeh ·
    Dear Prasad,

    I will start with the site survey, and if Lucas has any info he can elaborate more:

    Site Survey. The Contractor will ask the Specialist (Cladding Company) to complete the works. They agree on the Issue for Construction Drawings and these drawings go into the Cladding supplier system.

    The first thing the cladding supplier has to do it to get the Shop drawings approved. To do that, they need to get the exact dimensions from site. To get the exact dimensions, they need a professional surveyor to get the dimensions, elevations and levels for each opening, canopy, fins, etc that is within their scope of work.

    The professional surveyor submits their report to the Cladding Company (maybe it is made within the company) and they use the date in preparing the shop drawings.

    I always recommend verification at each step. Therefore, I would like for the Supervising Engineer to verify the Survey report in order to make sure that the data used for the preparation of the shop drawings is correct.

    With kind regards,

    Samer
  13. 0
    Mike Testro ·
    Hi Samer

    I have worked on cladding projects where there is enough tolerance designed into the secondary supports and bracketry for the cladding to track the vertical progress of the structure with a 3 level lag - it even works on insitu concrete.

    The onus is on the structure contractor to work within the contracted tolerances and delays occur when he gets it wrong.

    With other systems as you describe you have to complete the structure before measuring up the bracketry.

    Best regards

    Mike Testro
  14. 0
    Samer Zawaydeh ·
    Dear Mike,

    I understand what you are saying. If you have a big project, then you need the time and can work on standard sizes taking into consideration that the Construction must be within tolerance.

    On smaller projects, the requirements can be accommodated within 30-60 days of fabrication. It is must cheaper to wait until the openings are complete, then you take the actual dimensions.

    Yes, on small project we wait, on large projects fabrication proceeds as per approved drawings.

    With kind regards,

    Samer
  15. 0
    Prasad Ramanathan ·
    Hai Mike & Samer,

    Thank u for ur informations.If u can explain me the steps one by one for fin system,Spider System & dot point system it will be more helpful.

    Thanks & Regards
    Prasad Ramanathan
  16. 0
    Mike Testro ·
    Hi Prasad

    Sorry but I have never dealt with any of these systems.

    You need to check the method statements of the cladding firms.

    Otherwise try Google.

    Best regards

    Mike Testro
  17. 0
    Samer Zawaydeh ·
    Dear Prasad,

    The basic idea is that you have to understand the structural system and start from the Anchors, Main Members, Bracing, Secondary Members, then the cladding. And finally touch up and handing over.

    For the Fins, these are different shapes of solar blades ranging from 10cm to 100cm in width. They can come as 1 or two parts. What you need to do first is install the brackets in the right orientation as per drawings, then you install the Fin. The thing you need to watch out for is the quality of the work, they have to be watertight and they should not accumulate dust an their surfaces.

    The Spider System is a structural system. You need to install the brackets with anchors, then you need to install the Main Members, the is followed by the bracing and the secondary members, then you install the Glass panels. Finally you apply the mastic and make it water tights.

    The Dot Point is a new term. I can’t offer advice unless you tell me specifically what it is composed of.

    I would recommend that you visit the website of the major fabricator/ system that you are using. They must have a propress website that you can download all the technical information. Unless you are working with a secondary supplier in the market. In this case, I would recommend that you enter the websites of Major Suppliers in your area or worldwide and get to learn the details. All the information about any system they are using is free online or can be ordered easily. This is part of their marketing.

    With kinds regards,

    Samer
  18. 0
    Prasad Ramanathan ·
    Hai Samer,

    Thank u very much for ur informations.


    Regards
    Prasad Ramanathan
  19. 0
    Syed Rafiuddin ·

    Hi Guys can someone provide

    Hi Guys

     

    can someone provide installation productivity rates for Aluminium exterior cladding or composite material mashribiya type exterior cladding

     

    many thanks

    Syed

    email: moazzam_syed@yahoo.com

  20. 0
    Chandan Kumar Karan ·

    Hi Samer,  can you help for

    Hi Samer,

     

     

    can you help for facadae /aluminium/glass work production sequeanceing & installtion activity sequeance .

     

     

     

     

    BR

    CHAndan 

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?