Methanol Plant Equipment

Ahmed ElkordyMember for 18 years 3 months
Created
17
4
0
Dear all

It’s my first time working on a schedule for a methanol plant, and where I work there isn’t much experience in methanol plants either. I’m having trouble scheduling the enormous amount of equipment and package units within the plant. The available information from the BOQ include dimensions and Tons. So I was thinking of prioritizing and giving durations to- activities according to units tonnage.

Does anybody have experience in scheduling Methanol Plants construction? Any help would be highly appreciated.

17 replies

Oldest first
  1. 0
    Mike Testro ·
    Hi Ahmed

    I have no idea about ethanol plants either but common sense seems to indicate that there must be some sort of seqwuence for plant installation.

    In most industrial plants something goes in at one end and something different comes out the other.

    The plant would normally be installed in that sequence - tonnage has nothing to do with it.

    Surely you have a schematic layout of the plant showing where all the kit is placed?

    Best regards

    Mike Testro
  2. 0
    Ahmed Elkordy ·
    Like you said there must be some sort of sequence for plant installation. Although, why would it have anything to do with the sequence of the process itself? there’s no logic linking installation to operation.
    If for example a pump boosts water up a building, you don’t have to erect the pump then the pipes then the building.
    I studied the available information regarding the process but it’s not enough to do anything. I requested more information.
    I was thinking maybe sequencing according to tonnage so as to give activities invloving high manhours or prolonged cranes usage longer durations and later start dates in the submitted schedule to reduce risk.

    Thank you for replying.
  3. 0
    Mike Testro ·
    Hi Ahmed

    What about the structure that is holding the plant up?

    Is it already built?

    Best regards

    Mike Testro
  4. 0
    Samer Zawaydeh ·
    Dear Ahmed,

    Lets take it one step at a time and you can build it up accordingly.

    1. You need to have a meeting with all parting and agree on the Inspection and Test Plan for the project. This is usually done under the Project Manager umbrella and attended by the specialists.

    2. Material Submittals.
    3. Shop Drawings.
    4. Procurement
    5. Construction.
    6. Testing and Commissioning.

    Assuming that you are working for the Main Contractor, then the first thing that you need is to complete the Structure. Since the Structure is steel, then you need to complete the design of the steel structural and fabricate, treat and ship it to site. Accordingly, we have the following activities:

    a. Design of Steel Structure
    I. Submit Design Calcuation for all structures.
    II. Approve Desing Calculations for all structures: Main Members, Secondary Members, Connections, Bolts, nuts, flashing, cold formed sections, etc.

    b. Submit Shop drawings for approval.

    c. Fabricate the Steel Structure.
    This is done by monitoring the following activities (By Ton) each member:
    I. Procuring the Steel.
    II. Fabrication.
    III. Treatment (Painting or Galvanizing)
    IV. Shipping to Site.
    V. Arrival at site.

    It is recommended that you use a hand held scanner with bar coding for each member because you will have at least 30,000+ members for a such a plant.

    Once you have designed the steel structure, then you can know the loads for the design of the footings.

    Once the footings are designed then you can submit the following:

    A. Material for the Concrete design mix
    B. Shop drawings for the Footings.
    C. Site Layout and start of Excavation.
    D. Start Procurement of Steel.
    E. Start Construction.

    Under Construction you need to divide the project into areas or zones as per Layout.

    Then you creat a separte small schedule for each building or part as following

    1. Substructure
    a. Excavation
    b. Layout of Footings
    c. Shuttering of Footings.
    d. Reinforcement of Footings + installation of Anchor bolts.
    e. Inspection of works by Engineer
    f. Casting of Footings.
    g. Deshuttering.
    h. Insulation of footings.
    i. Fill in layers around footings+ Trench making if any.
    j. Casting of Blinding for Slab on Grade
    k. insulation of blinding
    l. Reinforcement of Slab on Grade
    m. Installation of E/M works.
    n. Inspection by Engineer
    o. Casting of Slab on Grade

    2. Superstructure
    i. Erection of Steel Columns
    ii. Erection of Beams and Rafts
    iii. Erection of secondary beams
    iv. insulation if any
    v. Cladding
    vi. Fire Protection of Columns
    vii. Cable Trays and ladders.

    You can repeat the above process for all levels until you reach the stacks.

    3. Electromechanical works.
    you will need to understand the systems
    1. Mechanical Systems
    Piping, Ducting, Fire Systems, etc
    2. Electrical Systems.
    Lighting, Power, Lighting Protection, Emergency, Fire Alarm, etc.

    4. Testing and Commissioning.
    Make sure that you read the specification and quality manuals.

    You need to read for 3-4 months and start building the Schedule part by part.

    Hope the information helped.

    With kind regards,

    Samer
  5. 0
    Ahmed Elkordy ·
    Dear Samer and Mike

    The Steel and Concrete structures are not the problem. My problem is the process equipment and package units (like the subject of the thread), that’s why i asked for someone with any experience in Methanol or similar plants.
    Anyway more information about the plant is underway.

    Thank you so much
  6. 0
    Samer Zawaydeh ·
    Dear Ahmed,

    Usually you can meet with the Designers of the Plant, and you can build your sequence of construction. Process Experts that will run the commissioning of the plant are usually the best source of information.

    From experience, I can assure you that even if you sit down with them in the same room for a year, they will not tell you the exact step by step requirements. This is privilaged information for the design company.


    Are you on the Contractor side?

    Best Regards,

    Samer
  7. 0
    Ahmed Elkordy ·
    Yes I’m working for the Contractor.
    And the project, and Engineer are in a different country :]

    I’m surprised to the limited amount of information on the internet regarding Methanol plants construction.

    I’m giving durations according to a factor I’m deriving that combines tonnage, dimensions and quantity. That, along with correcting special cases, I’m sure will yield....nothing! But it’s something until I get more data.

    Thanks
  8. 0
    Samer Zawaydeh ·
    Dear Ahmed,

    This is standard situation. Each party is in a different country. But with communication through email and phone, you can solve most of the problems. You need to identify the Project Manager with previous or similar knowledge, Designer, and the Key Expeditors with similar knowledge. Usually this will all available with the Engineering Company.

    Tonnage is used for the Fabrication and Erection of Steel. For piping, equipment and electrical works, it is better to use Nos and systems.

    Usually for plants such as this the basis requirement of the Employer would be for a modeling software for all systems. This is a 4-D model for all systems. It will enable you to track the design and the construction in 3D and with time. This is a basic requirements for plants.

    With kind regards,

    Samer
  9. 0
    Ahmed Elkordy ·
    Dear Samer

    Such software would indeed be very handy.
  10. 0
    Scarllet Pimpernel ·
    Dear Ahmed,

    For package units, you plan the shop drawing submission and approval, manufacturing duration, shipment (ETA).

    For site activities, you need to capture the installation, testing and commissioning.

    So, each package unit will be identified as 1 unit.

    with regards to piping, they norms for site installation monitoring is dia-inch.

    I hope this will help you.

    Thank you,
    Scarlett
  11. 0
    Ahmed Elkordy ·
    Thanks Scarlett


    Say the package unit includes pumps, tanks and equipment for that single package unit. So during procurement I’m dealing with it as a single unit. But when installing the contents of the package I would have to go through each item and estimate duration and manhours for it.
    So how come each package unit will be identified as 1 unit?

    I’m probably asking a stupid question but I’m not acquainted with such business. So I would like to thank you Mike, Samer and Scarlett for replying and trying to help.
  12. 0
    Samer Zawaydeh ·
    Dear Ahmed,
    That is a simple thing to do:

    PU1
    Construct Foundation
    Install Vibration Isolation Pads
    Install Machine
    Install Pumps
    Terminate Piping
    Terminate Electrical works
    Connect Duct Works
    Insulate Duct Works.
    Testing and Commissioning

    PU2
    PU3
    PU4
    etc

    You will add more or less the same items that are required for installation.

    Best Regards,

    Samer
  13. 0
    Gardson Duco ·
    Dear Ahmed,

    Package equipment installation procedure basically known during Engineering/Procurement phase. Usually first vendor information will arrive in engineering phase (since most data on this stage is standard designs) then final designs of equipments will usually comeup when 3D modeling is in 90%. By then orientation of piping, electrical , instrumentation, noozle oreintations etc will be finalized. Before your equipments/packages arrives on site for installation, everyhting is known.

    gardson
  14. 0
    Ahmed Elkordy ·
    Do you have any idea how I can get typical 3d models for such plant? Do they always require special software?
  15. 0
    Samer Zawaydeh ·
    Dear Ahmed,

    Yes they require special software. 10 years ago, they were costing around $50K. And it was a project requirement.

    If you check with your local Primavera Dealer, they might be able to lead you in the right direction.

    With kind regards,

    Samer
  16. 0
    Mazura Maarof ·

    Hi, If anyone can share

    Hi, If anyone can share schedule for Methanol Plant , that would be helpful. This is my email mazura_brennan@yahoo.com

    Thank you in advance.

  17. 0
    Mazura Maarof ·

    Hi, If anyone can share

    Hi, If anyone can share schedule for Methanol Plant , that would be helpful. This is my email mazura_brennan@yahoo.com

    Thank you in advance.