WBS

Jiso ThomasMember for 18 years 7 months
Created
1
4
0
Hi All,

I am bit confused with Importing informations in to Primavera P6.Do we need to import WBS as a Intergral part of all Imports.Can we import information with out WBS.Appreciate your response.

Thanks,

Jiso

1 reply

Oldest first
  1. 0
    Muhammad Anwar ·
    Jiso,

    Your question is not very clear. This is my guess!!!
    If you don’t want to bring in the WBS information for update or if you creating a new project through import wizard, after the ’import project options’ screen comes the project update options screen where you have layout name as default configuration. Through modify button you can change the WBS options. If you updating it will let you to change to ’Not import’ option.

    Hope this will help

    regards

    Muhammad