Unable to Put relations between activities!!

Basir AhmedMember for 17 years 7 months
Created
2
2
0
Hello everyone,

The subject seams to be a very odd one to ask on this portal but the problem is odder than it seems.

I was working on a schedule, had put all activities and their relations but all of a sudden my computer shuhtdown(not because of Primavera). I restarted the system and when i reopened the scheduled and started working on it, i was unable to add predecessors or successors to any activity.

Does anyone of you know what might the problem be.

Is there any check box that i/computer has checked or is there any option that makes all the activities to automatically start from the project start date? this might be the reason, if it is?

your help would be of much help.


Thankyou everyone.

With Kind Regards,

Basir Ahmed

2 replies

Oldest first
  1. 0
    Basir Ahmed ·
    Dear Sahul,

    This was the first thing that came to my mind.
    already check and done it.

    Although i have made th schedule once again, but knowing the problema nd its solution is the real issue.

    Regards,

    Basir Ahmed
  2. 0
    Shah. HB ·
    Hi

    I guess your access got locked i am not sure try opening the project in exclusive mode

Log in or join to reply