method of statement

Kamal Al-HouraniMember for 19 years 5 months
Created
12
4
0
As per the defenitions mentioned in the glossary of terms; Planning process defines how should activities be performed (methods). any one can clarify please.

and what are the method of statement in which planner shall prepare or participate in preparing???

thanks and Regards,
kamal.

12 replies

Oldest first
  1. 0
    Mike Testro ·
    Hi Kamal

    A Method Statement is a narrative that explains how the project is going to be built.

    Think of the programme as the picture and the Method Statement as the words.

    Best regards

    Mike Testro
  2. 0
    Kamal Al-Hourani ·
    Thank you Mike,
    in fact i know what method of statemnt is but my question is it neccessary that the planner should be the one who writes or prepares the method of statments taking into consideration that in some projects you will have all engineering disciplines there, so no way that the planner knows method of statemnt for civil, mechanical, electrical and instrumentations. am i right? please clarify.

    thanks and regards,
    kamal.
  3. 0
    Mike Testro ·
    Hi Kamal

    In most cases the method Statement precedes the plan.

    The person who plans the work should draft the Method Statement.

    That is not necessarily the same person who worked the software who may have just scheduled someone elses plan.

    Best regards

    Mike Testro
  4. 0
    Ferdinand U. ·
    hi all

    check this forum

    http://www.planningplanet.com/forum/forum_post.asp?fid=&Cat=5&Top=20208&page=4
  5. 0
    Anoon Iimos ·
    by the way Kamal, "method of statement" is different from "method statement" regardless if the same person made both

    a "method statement" maybe done by a specialist who knows the job (as Mike said); this specialist does not necessarily need to use or to know the software for scheduling
  6. 0
    Kamal Al-Hourani ·
    thank you all,
    Anoon, can you send me an example on "method statment" and another one on "method of statement"??

    thanks,
    kamal@altoukhi.com
  7. 0
    Santhosh kumar ·
    Hi Kamal,

    To me Method statement is a detail of the activities that you have in the planning(Schedule).For eg:You have an activity like erection of steel structure in the schedule.The Method statement will have all the details like how to do it, where you place the crane,safety measures etc.So a planner need not necessarily know all these things.


    Best Regards,

    Santhosh
  8. 0
    Kamal Al-Hourani ·
    hi kumar,
    do you mean that the method of statement is the work instructions and procedures required to do certain activity along with the health & safety, quality and specifications.... but method statement is the breakdown or steps needed to make one activity on a schedule??? Am I right???

    thanks,
    kamal.
  9. 0
    Mike Testro ·
    Hi Kamal

    Method Statement is how you do the work.

    Method of Statement is not a term I have heard before this thread - the only logical meaning is what method you use the draft the statement - pencil or ballpoint or keyboard.

    Best regards

    Mike Testro
  10. 0
    Santhosh kumar ·
    Hi Kamal,

    Whatever i mentioned in my earlier post is all about "method statement".
    There is nothing called "method of statement".


    Best Regards,

    Santhosh
  11. 0
    Santhosh kumar ·
    Hi Mike,

    Hahaha .Thats a good answer Mike.

    I was tired of hearing people using ’Method of statement’ instead of Method statement.


    Best Regards,

    Santhosh
  12. 0
    Anoon Iimos ·
    Hi Kamal,

    I agree with Mike and Santhosh, but I would suggest the question to be:

    What is the "method of statement" used to develop the "method statement"? I believe this has another meaning and relevance.

    cheers

Log in or join to reply