RESOURCE UNIT changed

JV AmandeMember for 18 years 7 months
Created
4
3
0

Hi guys;

Can you help me figure out, what’s happening with my resources. I’m having a problem with my resources after running the schedule.

Ex.

i input 1-unit of equipment or resource to a certain task. But after running/scheduling, it turns out to 0.01 sometimes 0.33, or it’s not whole number.

And eventually this will affect all my tabular/graphical reports.

WHY?

I am using a correct calendar.

Anyone can help me.

Thanks.

4 replies

Oldest first
  1. 0
    Mike Testro ·
    Hi JV

    What software are you using?

    Best regards

    Mike Testro
  2. 0
    Shah. HB ·
    Hi JV
    In P3 once you assign budgeted quantity ,it gets divided by activity original duration to get units per day ,the decimals you are talking about is unit per day I trust .


  3. 0
    JV Amande ·

    Shahul;

    Thanks for your idea, i am also aware of that. But i want to retain it to a whole number,

    say 1 day of task... then i input 1 unit of
    resource.

    After i run/schedule.. i recheck my resource/s and it turns out into 0.0~ something. It’s no whole number of unit.

    I encounter this just lately.

    Isn’t it the 1-unit of resource that i input should remain as 1-unit? How come it will become.. 0.0~ or not a whole number.


    Hi Mike;

    I’m only using P3.
  4. 0
    Vladimir Liberzon ·
    I don’t think that you will find a solution.
    In Spider Project there is special material property - discrete consumption. If it is not selected then materials are consumed in the proportion of the work done.
    I do not remember this feature in P3.
    Best Regards,
    Vladimir