Programme for 3B+G+M+18 office floor building

Vrinda MMember for 18 years 4 months
Created
6
3
0
Dear all,

Iam working on 3B+G+M+18 office floor building project having built up area 45,356m2 and height is 80.60m duration of 21 months.On left side of the building is another building of 53m and distance between the two buildings is 0.6m.The package includes enabling works & construction.

I would like to ask which are the problems faced bcoz of adjacent building and if u all can suggest some solution.

Enabling works : Shoring & Piling works excavation depth upto -14.8m.for shoring (secant piling)

Structure works : Shuttering on left side what is other than traditional formwork alternative for left side

Finishes : Blockwork ,plaster and paint how it will be done.

Please reply asap.

Thanks,
Vrinda.

6 replies

Oldest first
  1. 0
    Mike Testro ·
    Hi Vrinda

    Don’t forget:
    1. Air space clearance for the tower crane.
    2. Live services.
    3. Noise & dust restrictions.
    4. Access & delivery restrictions.
    5. Scaffolding space

    Best regards

    Mike Testro
  2. 0
    Samer Zawaydeh ·
    Dear Vrinda,

    You can also mention the following:

    1. Issue letters to all the service companies to identify the underground services available in the neighbourhood.

    2. You have to make sure that the insurance covers the adjacent buildings as well in addition to any piping and cables underneath.

    3. Underground footings of adjacent buildings. You might have to provide solution to situations that you might encounter.

    4. Traffic restrictions. Can your loaders and pumps arrive at site work 24/7.

    5. Do you have an movement joint between the two buildings and how did you include the treatment and cover in the scope of work.

    6. Disturbances to adjacent tenents. Do you have a sensitive operation next to your building like a Hotel or Hospital. People need to sleep at night.

    7. Do you have another Contractor at the same site? Are you going to share the working space, etc.

    8. How fast can you install your Tower cranes and how far is the laydown area.

    9. Safety and Health Plan. Make sure that it is reviewed by a professional.

    10. Get to know the site restrictions by inviting experienced supervisors to provide their input.

    With kind regards,

    Samer

  3. 0
    Vrinda M ·
    Dear Samer,
    Thanks a lot for your support !

    Vrinda.
  4. 0
    Samer Zawaydeh ·
    Dear Vrinda,

    One more issue that you have to solve is the insulation of the Basement walls below slab. The areas between the two buildings is 0.6m, can you lower your team and insulate the walls with Bitumin Rolls and then protection the insulation with protection boards and single size material or not.

    It would be good information to know what your design drawings are proposing. And if you can construct it or not.

    With kind regards,

    Samer
  5. 0
    Mukunda Y ·
    Vrinda

    I am also doing the same type of project. We got the Raft Botttom difference between the Buildings 1.5m. Retaining wall construction procedures we following is as follows.

    Retaing wall construction of Building 1
    Water proofing to retaingwall 1
    Block masonry to fill the gap
    Water proofing to Block masonry
    Retaining wall construction 2

    This is what we are following.....

    Cheers
  6. 0
    Samer Zawaydeh ·
    Dear mukunda,

    The 0.6m is not allowed as working space for 3-3.5 meters height wall. You can’t insulate the basement wall from outside. You need another solution!

    The sequence of activities should be as follow for the other three sides,

    Retaing wall construction of Building 1
    Water proofing to retaingwall 1
    -->Block masonry to protect the water proofing
    -->Compacted Fill in layers @250-300mm.
    Retaining wall construction 2

    With kind regards,

    Samer