Total float
In the Open Standard
Rola SabbahMember for 16 years 10 months
- Created
- 16
- 5
0
hi
hello every body, i need alittle help please:
regarding T.F, i have some activities that have a big TF, so what i did is linking them to other activities which is closer to the finish date or even to a critical activities, but i made sure that those activities early start is bigger than the activity with the big total float so it wont change the logic of the schedule, is that ok?
for example, i linked roof works with tiling side walks.
hello every body, i need alittle help please:
regarding T.F, i have some activities that have a big TF, so what i did is linking them to other activities which is closer to the finish date or even to a critical activities, but i made sure that those activities early start is bigger than the activity with the big total float so it wont change the logic of the schedule, is that ok?
for example, i linked roof works with tiling side walks.
16 replies
Oldest firstLog in or join to reply