Resource leveling: A practical approach
In the Open Standard
Carlos AranaMember for 17 years 4 months
- Created
- 9
- 2
0
Watch the next video
Lets create a scenario:
They must throw 30 cubic meters of sand from street level to roof level.
They start working in the morning at 8:00, then work 4 hours and then go to eat, they come an hour later and then they keep working from 13:00 to 17:00
Questions:
When are workers at street level free to work in another crew?
What is the shortest time when the work will be done?
I don’t have the answers, we must figure them out.
Best Regards,
Carlos.
Lets create a scenario:
They must throw 30 cubic meters of sand from street level to roof level.
They start working in the morning at 8:00, then work 4 hours and then go to eat, they come an hour later and then they keep working from 13:00 to 17:00
Questions:
When are workers at street level free to work in another crew?
What is the shortest time when the work will be done?
I don’t have the answers, we must figure them out.
Best Regards,
Carlos.
9 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?