Turnkey substation activities

Martin GomezMember for 16 years 5 months
Created
3
2
0
Hi all

I am new to this forum .i am an M&E Planner i do not have experience on High voltage substation planning (power transmission and distribution) .i would really appriciate if you could help me with a demo of how to plan a programme. Many thanks in advance

3 replies

Oldest first
  1. 0
    Dan Mårtensson ·
    Hi Sachin,

    Here is an example of WBS structur for a typical High voltage substation, turnkey.

    Project Management
    Purchase
    Manufacturing

    Lead Engineering

    Control & Protection
    Control and Protection Design
    Control and Protection Panels
    Marshalling and CT/VT Boxes
    Cable and Core Marking

    Layouts & Switchyards
    Design
    Purchase

    AC/DC
    AC/DC Design
    AC Switchgear
    DC Switchgear
    Battery
    Battery fuse boxes

    Logistics

    Civil design

    Site Works

    Enjoy

    //Dan


  2. 0
    Martin Gomez ·
    Thanks for your response dan.is there any way i can get hold of a sample programme.design,procurement,installation and testing and commissioning.cheers
  3. 0
    Dan Mårtensson ·
    Sachin

    There are diffrent program you can schedule in, for example:

    Microsoft Project
    Primavera
    Spider Project

    Regards

    Dan