Total time reqiured for Office building...
In the Open Standard
AN
Ashutosh Nema, PMPMember for 18 years 4 months
- Created
- 15
- 3
0
We have to give time frame(total duration) for one project having 2 basement having built up area 6700 sqm each and and 3 floors of built up area 7000 sqm each.It will used for office purpose, with all necessary landscape and MEP works. Total building lenth is about 180m with C shape.How much total time required to constuct this building. My accessment is 18 month. Is it OK for the prelimanary reports?
15 replies
Oldest first- 0HJHaresh Jayanth ·Total Duration reqd.
1)Foundation works - 80 days.
2) Basement- 2 - 45 days.
3) Basement - 1 - 30 days.
4) 3 Floors - 3X18 - 54 days.
5) Finishing works
after completion of - 210 days. (7 Months for office building)
Structure
Total reqd duration is = 420 days.i.e. 14 to 15 months, if the location is in Middleeast... - 0SZSamer Zawaydeh ·Dear Ashutosh,
I like what Haresh has provided. But you need to keep in mind that you have productivity factors, soil conditions, environmental factors, unforseen conditions and most important, it depends on the Contractor’s team that is going to be complete the project.
18-24 months is a good range. The choice depends on the client requirement as well. If you push the time, then the Contractors will increase the cost because they have to bring in more resources. So I suggest that you call up few contractor in your region and see what estimates they give you.
With kind regards,
Samer - 0MTMai Tawfeq ·Hi Haresh:
Your report has to show 2 work stages :
First one for foundation system : whether is piles with shoring works or whether is normal foundation , but whereas u have basement that mean shoring system will be applied and usually such system is required 6 months considering the factors which are mentioned by Samir .
And other stage for:
sub-structure : 3-4 months .
Super-structure : 2months .
Roof system :1 month.
Finishing with external packages 4 months since your building is offices.
The total will be; 15-16 months.
Regards .
Mai t.
- 0MTMike Testro ·Hi to All replies
When you list periods in weeks for various stages you are just guessing at top down durations - which is a dangerous practice.
You will not know the true duration until you have done a detailed bottom up critical path programme.
As I have said before in this forum the task should take little more that a day or two for a skilled planner and less than half a day for me.
Best regards
Mike Testro - 0AMArmando Moriles ·Guys, I would say...
1.Preparation and approval of priority shop drawings, bar bending schedules and delivery of first batch of rebar = 2 months from NTP
2. 1 month excavation works including final trimming to start 1 month from NTP
3.2 weeks blinding works (assuming raft foundation no piles) FS no. 2
4.Construct raft foundation 1 month SS no. 3 log 1 wk
5.Construct B2-B1 Columns and Retaining Walls 1 month SS no. 4 log 2 wks
6.Construct B1 Slabs and Beams 1 month SS 2 wks no. 5
7.Construct B1-GF Columns and Retaining Wall 1 month SS 2 wks no. 6
8.Construct GF Slabs and Beams 1 month SS 2 wks no. 7
9.The above shows total duration 4 months
10.L1 to Roof Deck= 2 months.
11.Total Civil/Structural Works duration is 6 months from NTP
12.Plumbing and Electrical SS no. 4 for 8 months
13.Mechanical and Fire Protection FS no. 6 for 6 months
14.Architectural Works 7 months FS no. no. 6 for 6 months
15.External Finishing Works and Landscaping 4 months FS 10
16.Total Project Duration is 9 months
As the duration becomes shorter, the prelims/overhead costs also becomes cheaper.
Mike, as I read your reply less than an hour ago, your comments regarding dangerous practice of a planning engineer is very much appreciated. However, maybe plenty or few members like me are excited to read what others have in their minds for this topic. And as the information flows freely I mean the replies, we could decide which information is likely to caught our attention or not.
Best regards,
Arman - 0AMArmando Moriles ·Hi Samer,
I would use the following:
1 floor set of table forms
2 floor sets of back props
3 mobile cranes for erection (no tower crane)
with the above, the cycle could be 7 days/floor which gives us 42 days from B2 to RD but say 2 months for learning curve,etc.
As what Mike said, it is indeed a simple structure. I would prefer to have the shortest construction duration to significantly reduce the prelims cost.
regards,
arman
- 0MTMike Testro ·Hi Armando
If you can spring the columns from the pile caps or the raft you can work in level 0 as soon as level 1 is de-propped.
This allows drains and services and the basement slab and lift pit to be carried out concurrent with the structure.
This should take off 4 weeks.
Best regards
Mike Testro - 0SZSamer Zawaydeh ·Dear Mike,
These projects are fun, I was part of a project recently and we were able to complete 6700m2 building (6 stories) with 18meter excavation in 6 months ($2 Million).
We have around 70 people at site working 20 hours a day with the necessary materials and equipment to complete the job. 3 Project Managers and steady finance.
With kind regards,
Samer - 0AMArmando Moriles ·Hi Mike,
Your right, top-down is not a viable option.
It is only a 3 storey bldg so the equipments are not that big. A trolley system using basement ramp could be used to install and remove the equipments. Another option is to assymble the equipments at the basement ex. chiller if any.
regards,
arman