SECQUENCE FOR INTERNAL FINISHES
In the Open Standard
Ponnaganti SridharMember for 22 years 2 months
- Created
- 2
- 4
0
Hi! guys
i am having a very stupid vague dought , i am very sorry for keeping such a basic question... but it important for me at this time to conform form our planner’s teams.
in a building project (which i am working on now)
can we start plastering after 3 days start of and finish it after 3 days of block work.
or is it required to start plaster after completion of total block work and waiting for 3 weeks (for curing) and then start
plater then (that is what my P.M wants)
i am having a very stupid vague dought , i am very sorry for keeping such a basic question... but it important for me at this time to conform form our planner’s teams.
in a building project (which i am working on now)
can we start plastering after 3 days start of and finish it after 3 days of block work.
or is it required to start plaster after completion of total block work and waiting for 3 weeks (for curing) and then start
plater then (that is what my P.M wants)
2 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?