Can anybody suggest which is best method to produce s curves for schedule not loaded without resources or cost

Thanks in advance

2 replies

Oldest first
  1. 0
    Rodel Marasigan ·
    Manoj,
    You cannot produce S-Curve without resource or cost loading.
    Below link is where I explain how to use duration and convert to cost loading so you can produce S-Curve
    Duration % Complete Post #3
  2. 0
    Samer Zawaydeh ·
    Dear Manoj,

    The S-Curve is an accummulation of numbers. What is it that you want to represent in the S-curve. If you are talking about progress, how are you reporting the progress on the activities.

    With kind regards,

    Samer